3. Someone leaves: count the work still left

Lesson 3 of 57 minFree

Today’s goal: split the question into stages when a worker leaves. Separate work completed from work left.

Together A and B do 5 units/day. Total work is 30 units. After 2 days, how much is left?

A 10 units
B 25 units
C 20 units
D 28 units
Show answer

Correct answer: C

Done = 5 × 2 = 10. Left = 30 − 10 = 20.

Option A: 10 is completed work.

Option B: 25 subtracts only one day’s work.

Option D: Subtract work-units, not days.

Hint: Find completed work first.

Follow the work

A takes 6 days alone; B takes 12. They work together for 2 days, then B leaves. Use 12 total units. A does 2/day; B does 1/day.

StageWho works?Work
First 2 daysA + B, 3 units/day6 units completed
B has leftA alone, 2 units/day6 units remain

Solve in two stages

  1. Together for 2 days: (2 + 1) × 2 = 6 units completed.
  2. Work left: 12 − 6 = 6 units.
  3. A alone: 6 ÷ 2 = 3 MORE days.
  4. TOTAL time: 2 days already spent + 3 more = 5 days.

Finish the last step

B leaves. 6 units remain; A alone does 2 units/day. How many MORE days are needed?

A 3 days
B 5 days
C 2 days
D 12 days
Show answer

Correct answer: A

Extra time = 6 ÷ 2 = 3 days.

Option B: Earlier days are added only when total time is asked.

Option C: 2 is the daily rate, not the remaining time.

Option D: Divide remaining work by the daily rate.

Hint: Use the rate of the worker still present.

Make your own two-stage table

A takes 8 days alone, B takes 24. They work together for 3 days, then B leaves. How many MORE days does A need?

A 3 days
B 7 days
C 6 days
D 4 days
Show answer

Correct answer: D

Total 24; rates 3 and 1. Done in 3 days = 12; left = 12. A needs 12 ÷ 3 = 4 more days.

Option A: 3 days were already spent together.

Option B: 7 is total time: 3 + 4.

Option C: Find remaining work and divide by A’s rate.

Hint: Separate the two-worker and one-worker stages.

A takes 10 days alone, B takes 15. They work together for 3 days, then B leaves. What is the TOTAL time from the start?

A 5 days
B 8 days
C 6 days
D 10 days
Show answer

Correct answer: B

Total 30; rates 3 and 2. Together complete 15 units in 3 days. A needs 15 ÷ 3 = 5 more days. Total = 3 + 5 = 8.

Option A: 5 is extra time only.

Option C: 6 assumes both work to the end.

Option D: 10 ignores B’s help during the first 3 days.

Hint: Underline TOTAL.

Catch three mistakes: using both rates after one worker leaves; dividing completed work instead of work left; giving extra days when total time was asked.

Before moving on, explain whose rate you use after B leaves, and why.